Fix 19 nails or screws per sheet to have a longlasting and guaranteed roof.
Onduline roofing sheets overlap.
Onduline roofing only comes in one length 2m x 0 95m so your first port of call should be to ensure that you have enough material for the job.
The run is the horizontal distance of the ridge from the eave.
Begin every second raw with a sheet cut in half vertically.
Stagger the rows by starting the second row with a half sheet see in drawing the sheet 4.
The ridge element should overlap the onduline sheet at minimum 14 cm.
Get your measurements right.
The slope of the roof can be calculated from measurements of the rise and run of the roof.
The roof slop is often stated as the inches of vertical rise per 12 inches of horizontal run length.
Of course sheets can be cut but there s a minimum requirement for overhang 70mm at the eaves and pitching 5 degrees.
Overlap 12 cm 3.
Start fixing sheets at the opposite to prevailing winds end of the roof.
Overlap and side overlap.
15 fixings minimum should be used per sheet.
The rise if the vertical distance of the ridge above the eave.
Lay ridge elements with a minimum overlap of 12 5 cm.
Ensure watertightness at ridge by applying the onduvilla foam fillers on both sides of the ridge line.
Up signs indicate the direction of the ridge to lay the sheets correctly.
To have a long lasting and guaranteed roof it is mandatory to follow the nailing order and pattern ridges start fixing the ridge element opposite to the prevailing winds end of the roof.
The direction of the overlap is opposite to the direction of the prevailing winds.
Ensure waterproofing by aligning the overlapping lines.